How Long Does an Extension Actually Take?
A single-storey extension typically takes 8 to 12 weeks from groundworks to handover: roughly 2 weeks for groundworks and foundations, 3 weeks for structure and roof, 2 weeks for windows, doors and first fix, and 3 to 5 weeks for plastering, second fix and decoration.
Timescale is one of the most common questions we get asked, and the honest answer is that it depends on size and specification, but here is a realistic breakdown for a typical single-storey rear extension of around 25-30m².
**Weeks 1-2: Groundworks and foundations.** Excavation, foundation pour and drainage. Weather-dependent, so this stage has the most potential for minor delay.
**Weeks 3-5: Structure and roof.** Brickwork up to roof level, structural steel where needed, and the roof structure and covering. Once the roof is on, the build is "weathertight" and less exposed to weather delays.
**Weeks 6-7: Windows, doors and first fix.** Windows and external doors fitted, and first-fix electrics and plumbing installed behind walls and under floors.
**Weeks 8-12: Plastering, second fix and decoration.** Plastering (which needs drying time), then second-fix electrics and plumbing (sockets, switches, taps, radiators), flooring, and final decoration.
We give you a specific, realistic programme as part of your written quote, with a weekly update once work starts so you always know exactly where the project stands.